Thursday 19th January 2017

Power Infrastructure Maintenance, scheduled 1 year ago

==Update == Maintenance works have been successfully completed. No issues were discovered during the maintenance.

We are conducting essential maintenance on one of our generators at DCN1 between 08:00 and 16:00 on 20th January 2017; we expect the maintenance to take around 3 hours to complete.

During this period the generator will be disconnected from our power infrastructure. To ensure we have redundancy in case of a power outage, a temporary generator will be installed during the works.

A full RAMS (Risk Assessment and Method Statement) has been produced in line with our facilities management procedures. Risks classified as high have been evaluated and all actions, within reason, to minimise their risk taken.

We anticipate no disruption to service during this time, and if during the maintenance any issues are identified we will provide updates on our status page www.cwcsstatus.co.uk.